Owner
WV DOT
Contractor
Flatiron
Designer
RS&H, COWI
Our Role
McNary Bergeron is providing construction engineering services to the Design-Build Team. This includes analysis and procedures for the float-in of the tied arch main span which will be constructed offsite.
Total Contract Value
$131 million
Timeline
2018 - 2021
Construction Method and Specifications
The span will be loaded onto barges outfitted with ALE jacking systems and then floated downstream and onto its final bearing locations at the project site.