Owner
Arrow WV, Inc.
Contractor
Freyssinet USA
Designer
Schlaich Bergermann and Partner / Hatch Mott MacDonald
Our Role
Independent Review of Construction Equipment and Erection methods
Total Contract Value
$15 million
Timeline
2011 - 2013
Construction Method and Specifications
Access to the site with heavy equipment is limited to the areas near the abutments and piers. As a result, a temporary cable crane is required to move the steel superstructure segments into position within the span. The cable crane is supported on temporary saddles at each of the piers. A hoisting trolley lifts segments delivered near the piers and moves them into position where they are erected on the main cables. Extensive temporary works and equipment is required to stabilize the piers, install the permanent cables, install the cable crane, and erect the superstructure segments.