Owner
NC Department of Transportation
Contractor
PCL Construction
Designer
HDR
Our Role
McNary Bergeron & Associates was responsible for templates, seal slabs, precast column platforms, falsework removal, trestle, girder erection/stability, and barge stability/loading procedures.
Total Contract Value
$252 million
Timeline
2016-2018
Construction Method and Specifications
Precast substructure and seal slab