MIC/Earlington Heights Connector

Miami, FL

Project Description

The MIC/Earlington Heights Connector Metro rail Extension consists of 2.4 miles of elevated dual track guideway, one Metro rail station at the MIC, and a bus terminal plaza.

Owner

Miami Dade Transit

Contractor

Odebrecht w/ Rizanni de Echer as Segmental Subcontractor

Designer

URS

Our Role

Provided Redesign Engineering and Construction Engineering to the Segmental Subcontractor, Rizanni de Echer.

Total Contract Value

Segmental: ~$50,000,000

Timeline

NTP: May 2009 Completion: December 2011

Construction Method and Specifications

Precast Segmental built using Balanced Cantilever Construction. The project consists of 13 units with approximately 40 spans and 1000 segments.

Awards

2013 ASBI Bridge Award of Excellence