Bridges to Prosperity McNary Bergeron

PROJECT HIGHLIGHTS: BRIDGE 50

Our Role

McNary Bergeron is providing construction engineering services including geometry control, construction analysis, and integrated shop drawing templates. We also independently verified several aspects of the design.

Construction Method and Specifications

-Twin 15-span bridges
-Single box precast segmental
-Ground based crane erected balanced cantilever
-Overhead erection gantry
-38m typical span length
-11.4m deck width

Owner

Yefe Nof Transportation Infrastructure and Constructions Ltd.

Contractor

Solel Boneh

Timeline

August 2010 - Summer 2013

Data Sheet (pdf)