PROJECT HIGHLIGHTS: HONOLULU TRANSIT (FARRINGTON)

The Honolulu Rail Transit Project is a 20-mile elevated rail line that will connect West O`ahu beginning at East Kawith downtown Honolulu and Ala Moana Center. It will provide residents with a fast, reliable and affordable transportation alternative. All 21 stations will be fully compliant with the Americans with Disabilities Act (ADA) having high-level platforms (same level as the vehicle floor) stairs, escalators and elevators featured at each station.

Our Role

McNary Bergeron & Associates is providing construction engineering support to the contractor including:

-Independent design review of the precast span-by-span (SBS) and cast-in-place (CIP) balanced cantilever structures.
- Geometry control and monitoring for the CIP balanced cantilever structure.
- Analysis and review of the SBS construction loads.
- Design of temporary supports for construction of the CIP balanced cantilever structure.
- Independent review of the CIP balanced cantilever form travelers.

Owner

HART Honolulu Authority for Rapid Transportation

Contractor

Kiewit

Designer

Figg

Timeline

2011-2015