PROJECT HIGHLIGHTS: MIC / EARLINGTON HEIGHTS CONNECTOR - MIAMI, FLORIDA

The MIC/Earlington Heights Connector Metrorail Extension consists of 2.4 miles of elevated dual track guideway, one Metrorail station at the MIC, and a bus terminal plaza.

Our Role

Provided Redesign Engineering and Construction Engineering to the Segmental Subcontractor, Rizanni de Echer

Construction Method and Specifications

Precast Segmental built using Balanced Cantilever Construction. 13 units, Approx 40 spans, Approximately 1000 Segments

Owner

Miami Dade Transit

Contractor

Odebrecht w/ Rizanni de Echer as Segmental Subcontractor

Designer

URS

Total Contract Value

Segmental: ~$50,000,000

Timeline

NTP: May 2009
Completion: December 2011